Spring Maintenance Retrospective
AI summary
Spring maintenance ran 4 days late. Root cause: Vertex delivery delay + inspection recalibration. New policy: 25% buffer on vendor-dependent windows.
Spring maintenance ran four days over schedule. Root cause was the late delivery of the spindle assembly from Vertex (see Q3 review). Secondary issue: we underestimated the time required to recalibrate the inspection station after the new lighting was installed. Going forward, we are baking a 25 percent buffer into any maintenance window where vendor parts are involved.