Floor 3 Robotics Cell Commissioning Plan
AI summary
Floor 3 robotics commissioning over 4 weeks. Daniel leads. Operator training by W33. ISO 10218 hazard framework. Anna auditing.
The Floor 3 robotics cell goes live in week 34. Commissioning sequence: power and pneumatic certification week 32, dry-run cycles week 33, first-article production week 34, full release week 35. Daniel is on point. Operator training runs in parallel and must be complete by end of week 33. Safety officer sign-off required at each stage. We are using the ISO 10218 framework for hazard analysis. Anna is auditing.